Quantcast
Channel: Free Homework's Help 24/7
Viewing all 553 articles
Browse latest View live

Problem 8-7 Calculating NPV and IRR [LO 3, 4] A project that provides annual cash flows of $2,800 for nine years costs $9,200 today. Requirement 1: At a required return of 11 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)

$
0
0
Problem 8-7 Calculating NPV and IRR [LO 3, 4]
A project that provides annual cash flows of $2,800 for nine years costs $9,200 today.

Requirement 1:
At a required return of 11 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g.,32.16).)

  NPV  $  

Requirement 2:
At a required return of 27 percent, what is the NPV of the project? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g.,32.16).)

  NPV  $  

Requirement 3:
At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)

  Discount rate %  


Explanation:

Problem 8-8 Calculating IRR [LO 3] Consider the following cash flows: Year Cash Flow 0 –$ 32,000 1 14,200 2 17,500 3 11,600

$
0
0
Problem 8-8 Calculating IRR [LO 3]
Consider the following cash flows:

YearCash Flow
0 –$ 32,000 
1   14,200 
2   17,500 
3   11,600 


Required:
What is the IRR of the above set of cash flows?(Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)

  Internal rate of return %  


Explanation:
The IRR is the interest rate that makes the NPV of the project equal to zero. So, the equation that defines the IRR for this project is:
 
0 = – $32,000 + $14,200 / (1 + IRR) + $17,500 / (1 + IRR)2 + $11,600 / (1 + IRR)3
 
Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:
 
IRR = 17.32%
   
Calculator solution:
 
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation.
  
CFo
 –$32,000
C01
 $14,200
F01
 1
C02
 $17,500
F02
 1
C03
 $11,600
F03
 1
  IRR CPT
  17.32%

Problem 8-9 Calculating NPV [LO 4] Consider the following cash flows: Year Cash Flow 0 –$ 32,000 1 14,200 2 17,500 3 11,600

$
0
0
Problem 8-9 Calculating NPV [LO 4]
Consider the following cash flows:

YearCash Flow
0 –$ 32,000
1   14,200 
2   17,500 
3   11,600 


Requirement 1:
What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations.)
Net present value$  

Requirement 2:
What is the NPV at a discount rate of 10 percent? (Do not round intermediate calculations.Round your answer to 2 decimal places (e.g.,32.16).)

  Net present value$  

Requirement 3:
What is the NPV at a discount rate of 20 percent? (Do not round intermediate calculations. Negative amount should be indicated by a minus sign.Round your answer to 2 decimal places (e.g., 32.16).)

  Net present value$  

Requirement 4:
What is the NPV at a discount rate of 30 percent? (Do not round intermediate calculations. Negative amount should be indicated by a minus sign.Round your answer to 2 decimal places (e.g., 32.16).)

  Net present value$  


Explanation:
1:
The NPV of a project is the PV of the outflows plus the PV of the inflows. At a zero discount rate (and only at a zero discount rate), the cash flows can be added together across time. So, the NPV of the project at a zero percent required return is:
 
NPV = – $32,000 + 14,200 + 17,500 + 11,600
NPV = $11,300
 
2:
The NPV at a 10 percent required return is:
 
NPV = – $32,000 + $14,200 / 1.10 + $17,500 / 1.102 + $11,600 / 1.103
NPV = $4,087.15
 
3:
The NPV at a 20 percent required return is:
 
NPV = – $32,000 + $14,200 / 1.20 + $17,500 / 1.202 + $11,600 / 1.203
NPV = –$1,300.93
 
4:
And the NPV at a 30 percent required return is:
 
NPV = – $32,000 + $14,200 / 1.30 + $17,500 / 1.302 + $11,600 / 1.303
NPV = – $5,441.97
 
Notice that as the required return increases, the NPV of the project decreases. This will always be true for projects with conventional cash flows. Conventional cash flows are negative at the beginning of the project and positive throughout the rest of the project.
   
Calculator solution:
 
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation.
  
CFo
 –$32,000
CFo
 –$32,000
C01
 $14,200
C01
 $14,200
F01
 1
F01
 1
C02
 $17,500
C02
 $17,500
F02
 1
F02
 1
C03
 $11,600
C03
 $11,600
F03
 1
F03
 1
  I = 0%  I = 10%
  NPV CPT  NPV CPT
  $11,300.00  $4,087.15
   
CFo
 –$32,000
CFo
 –$32,000
C01
 $14,200
C01
 $14,200
F01
 1
F01
 1
C02
 $17,500
C02
 $17,500
F02
 1
F02
 1
C03
 $11,600
C03
 $11,600
F03
 1
F03
 1
  I = 20%  I = 30%
  NPV CPT  NPV CPT
  –$1,300.93  –$5,441.97

Kerron Company is presented with the following two mutually exclusive projects. The required return for both projects is 19 percent. Year Project M Project N 0 –$140,000 –$355,000 1 63,500 152,500 2 81,500 180,000 3 72,500 137,500 4 58,500 110,000

$
0
0
Kerron Company is presented with the following two mutually exclusive projects. The required return for both projects is 19 percent.

YearProject MProject N
0–$140,000     –$355,000     
1 63,500      152,500     
2 81,500      180,000     
3 72,500      137,500     
4 58,500      110,000     


Required:
(a)
What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percentage rounded to 2 decimal places (e.g.,32.16).)

    IRR  
  Project M %  
  Project N %  


(b)
What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).)

        NPV  
  Project M$  
  Project N$  


(c)Which, if either, of the projects should the company accept?
  
 Project M


Explanation:(a)
The IRR for each project is:

  M: $140,000 = $63,500 / (1 + IRR) + $81,500 / (1 + IRR)2 + $72,500 / (1 + IRR)3 + $58,500 / (1 + IRR)4

Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:

IRR = 34.47%

  N: $355,000 = $152,500 / (1 + IRR) + $180,000 / (1 + IRR)2 + $137,500 / (1 + IRR)3 + 110,000 / (1 + IRR)4

Using a spreadsheet, financial calculator, or trial and error to find the root of the equation, we find that:

IRR = 24.61%

The IRR decision rule implies we accept project M because the IRR for M is greater than the IRR for N.

(b)
The NPV for each project is:


  M: NPV = – $140,000 + $63,500 / 1.19 + $81,500 / 1.192 + $72,500 / 1.193 + $58,500 / 1.194
 NPV = $43,108.55

  N: NPV = – $355,000 + $152,500 / 1.19 + $180,000 / 1.192 + $137,500 / 1.193 + $110,000 / 1.194
 NPV = $36,709.17

The NPV criterion implies we accept project M because project M has a higher NPV than project N.

(c)
Accept project M since the NPV is higher. IRR cannot be used to rank mutually exclusive projects.
   
Calculator Solution:
 
Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation.
    
Project M   
CFo
 –$140,000
CFo
 –$140,000
C01
 $63,500
C01
 $63,500
F01
 1
F01
 1
C02
 $81,500
C02
 $81,500
F02
 1
F02
 1
C03
 $72,500
C03
 $72,500
F03
 1
F03
 1
C04 $58,500C04 $58,500
F04 1F04 1
  CPT IRR  I = 19
  34.47%  NPV CPT
   $43,108.55
   
Project N   
CFo
 –$355,000
CFo
 –$355,000
C01
 $152,500
C01
 $152,500
F01
 1
F01
 1
C02
 $180,000
C02
 $180,000
F02
 1
F02
 1
C03
 $137,500
C03
 $137,500
F03
 1
F03
 1
C04 $110,000C04 $110,000
F04 1F04 1
  CPT IRR  I = 19
  24.61%  NPV CPT
   $36,709.17

Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 11 percent.

$
0
0
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 11 percent.

Year  Project F  Project G
0–$ 139,000     –$ 209,000     
1  58,000       38,000     
2  52,000       53,000     
3  62,000       92,000     
4  57,000       122,000     
5  52,000       137,000     


Required:
(a)
Calculate the payback period for both projects. (Do not round intermediate calculations.Round your answers to 2 decimal places (e.g., 32.16).)

 Payback period
  Project F years  
  Project G years  


(b)
Calculate the NPV for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).)

 Net present value
  Project F$    
  Project G$    


(c)Which project should the company accept?
  
  Project G


Explanation:

Problem 8-1 Calculating Payback [LO 1] Consider the following cash flows: Year Cash Flow 0 –$6,800 1 1,950 2 4,100 3 1,750 4 1,450

$
0
0
Problem 8-1 Calculating Payback [LO 1]
Consider the following cash flows:

Year Cash Flow
0–$6,800        
1 1,950        
2 4,100        
3 1,750        
4 1,450        


Required:
What is the payback period for the above set of cash flows? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)

  Payback period years  


Explanation:
To calculate the payback period, we need to find the time the project needs to recover its initial investment. After two years, the project has created:
 
$1,950 + 4,100 = $6,050
 
in cash flows. The project still needs to create another:
 
$6,800 – 6,050 = $750
 
in cash flows. During the third year, the cash flows from the project will be $1,750. So, the payback period will be 2 years, plus what we still need to make divided by what we will make during the third year. The payback period is:
 
Payback = 2 + ($750 / $1,750)
Payback = 2.43 years

“Major” funds include a. all governmental funds plus proprietary funds that have fund balances greater than 10% of those of all proprietary funds combined b. the general fund, special revenue funds, capital projects funds, and debt service funds c. the general fund plus all funds having assets greater than 50% of those of the general fund d. the general fund plus other funds in which total assets, revenues, or expenditures/expenses of the fund are at least 10% of the corresponding total for the relevant fund category (governmental or enterprise) and also at least 5% of the corresponding total for all governmental and enterprise funds combined

$
0
0
“Major” funds include
a. all governmental funds plus proprietary funds that have fund balances greater than 10% of those of all proprietary funds combined
b. the general fund, special revenue funds, capital projects funds, and debt service funds
c. the general fund plus all funds having assets greater than 50% of those of the general fund
d. the general fund plus other funds in which total assets, revenues, or expenditures/expenses of the fund are at least 10% of the corresponding total for the relevant fund category (governmental or enterprise) and also at least 5% of the corresponding total for all governmental and enterprise funds combined

                                       

Answer
the general fund plus other funds in which total assets, revenues, or expenditures/expenses of the fund are at least 10% of the corresponding total for the relevant fund category (governmental or enterprise) and also at least 5% of the corresponding total for all governmental and enterprise funds combined

Internal service funds are reported as a. business-type activities in government-wide statements and governmental funds in funds statements b. proprietary funds in funds statements and governmental activities in government-wide statements c. business-type activities in government-wide statements and proprietary funds in funds statements d. governmental funds in funds statements and governmental activities in government-wide statements

$
0
0
Internal service funds are reported as
a. business-type activities in government-wide statements and governmental funds in funds statements
b. proprietary funds in funds statements and governmental activities in government-wide statements
c. business-type activities in government-wide statements and proprietary funds in funds statements
d. governmental funds in funds statements and governmental activities in government-wide statements

Answer


proprietary funds in funds statements and governmental activities in government-wide statements

Account classifications include assets, liabilities, stockholders’ equity, dividends, revenues, and expenses. Required: For each transaction, select whether the related account would be classified as an asset, liability, or stockholders’ equity to be reported in the balance sheet; a revenue or expense to be reported in the income statement; or a dividend to be reported in the statement of stockholders’ equity.

$
0
0
Account classifications include assets, liabilities, stockholders’ equity, dividends, revenues, and expenses.

Required:
For each transaction, select whether the related account would be classified as an asset, liability, or stockholders’ equity to be reported in the balance sheet; a revenue or expense to be reported in the income statement; or a dividend to be reported in the statement of stockholders’ equity.


Raner, Harris, & Chan is a consulting firm that specializes in information systems for medical and dental clinics. The firm has two offices—one in Chicago and one in Minneapolis. The firm classifies

Next: For each of the following, compute the future value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 2,500 12 12 % $ 9,252 6 10 81,355 13 11 188,796 7 7 Explanation: To find the FV of a lump sum, we use: FV = PV(1 + r)t FV = $2,500(1.12)12 = $ 9,739.94 FV = $9,252(1.10)6 = $ 16,390.48 FV = $81,355(1.11)13 = $ 315,924.26 FV = $188,796(1.07)7 = $ 303,165.12 Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 12 12% ±$2,500 N I/Y PV PMT FV Solve for $9,739.94 Enter 6 10% ±$9,252 N I/Y PV PMT FV Solve for $16,390.48 Enter 13 11% ±$81,355 N I/Y PV PMT FV Solve for $315,924.26 Enter 7 7% ±$188,796 N I/Y PV PMT FV Solve for $303,165.12
$
0
0
Raner, Harris, & Chan is a consulting firm that specializes in information systems for medical and dental clinics. The firm has two offices—one in Chicago and one in Minneapolis. The firm classifies the direct costs of consulting jobs as variable costs. A contribution format segmented income statement for the company's most recent year is given below:

Office
Total CompanyChicagoMinneapolis
  Sales$600,000100%  $120,000100%  $480,000100%  
  Variable expenses
324,000
54%  
36,000
30%  
288,000
60%  
  Contribution margin276,00046%  84,00070%  192,00040%  
  Traceable fixed expenses
134,400
22%  
62,400
52%  
72,000
15%  
  Office segment margin141,60024%  
$21,600
18%  
$120,000
25%  
  Common fixed expenses not
      traceable to offices
96,00016%  
  Net operating income
$45,600
8%  


Refer to the original data. Assume that sales in Chicago increase by $40,000 next year and that sales in Minneapolis remain unchanged. Assume no change in fixed costs. Prepare a new segmented income statement for the company. (Round your percentage amounts to 2 decimal places. Input all amounts as positive value. Omit the "$" and "%" signs in your response.)

Segments
Total CompanyChicagoMinneapolis
Amount%Amount%Amount%
  Sales$   $   $   
  Variable expenses
 
 
 
 
 
 
  Contribution margin      
  Traceable fixed expenses
 
 
 
 
 
 
  Office segment margin  
$  
 
$  
 
  Common fixed expenses
     not traceable to segments
  
  Net operating income
$  
 

For each of the following, compute the future value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 2,500 12 12 % $ 9,252 6 10 81,355 13 11 188,796 7 7 Explanation: To find the FV of a lump sum, we use: FV = PV(1 + r)t FV = $2,500(1.12)12 = $ 9,739.94 FV = $9,252(1.10)6 = $ 16,390.48 FV = $81,355(1.11)13 = $ 315,924.26 FV = $188,796(1.07)7 = $ 303,165.12 Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 12 12% ±$2,500 N I/Y PV PMT FV Solve for $9,739.94 Enter 6 10% ±$9,252 N I/Y PV PMT FV Solve for $16,390.48 Enter 13 11% ±$81,355 N I/Y PV PMT FV Solve for $315,924.26 Enter 7 7% ±$188,796 N I/Y PV PMT FV Solve for $303,165.12

Next: For each of the following, compute the present value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future value $ 12 6 % $ 15,051 3 12 47,557 28 13 882,073 30 10 546,164 Explanation: To find the PV of a lump sum, we use: PV = FV / (1 + r)t PV = $15,051 / (1.06)12 = $ 7,479.89 PV = $47,557 / (1.12)3 = $ 33,850.13 PV = $882,073 / (1.13)28 = $ 28,794.41 PV = $546,164 / (1.10)30 = $ 31,299.87 Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 12 6% $15,051 N I/Y PV PMT FV Solve for $7,479.89 Enter 3 12% $47,557 N I/Y PV PMT FV Solve for $33,850.13 Enter 28 13% $882,073 N I/Y PV PMT FV Solve for $28,794.41 Enter 30 10% $546,164 N I/Y PV PMT FV Solve for $31,299.87
$
0
0
For each of the following, compute the future value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)):

Present ValueYearsInterest RateFuture Value
$2,50012     12%$  
9,2526     10 
81,35513     11 
188,7967     7 



Explanation:

For each of the following, compute the present value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future value $ 12 6 % $ 15,051 3 12 47,557 28 13 882,073 30 10 546,164 Explanation: To find the PV of a lump sum, we use: PV = FV / (1 + r)t PV = $15,051 / (1.06)12 = $ 7,479.89 PV = $47,557 / (1.12)3 = $ 33,850.13 PV = $882,073 / (1.13)28 = $ 28,794.41 PV = $546,164 / (1.10)30 = $ 31,299.87 Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 12 6% $15,051 N I/Y PV PMT FV Solve for $7,479.89 Enter 3 12% $47,557 N I/Y PV PMT FV Solve for $33,850.13 Enter 28 13% $882,073 N I/Y PV PMT FV Solve for $28,794.41 Enter 30 10% $546,164 N I/Y PV PMT FV Solve for $31,299.87

Next: Solve for the unknown interest rate in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 280 5 % $ 372 400 19 1,370 43,000 20 238,809 42,261 30 1,107,073 Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for r, we get: r = (FV / PV)1 / t – 1 FV = $372 = $280(1 + r)5; r = ($372 / $280)1/5 – 1 = 0.0585, or 5.85% FV = $1,370 = $400(1 + r)19; r = ($1,370 / $400)1/19 – 1 = 0.0669, or 6.69% FV = $238,809 = $43,000(1 + r)20; r = ($238,809 / $43,000)1/20 – 1 = 0.0895, or 8.95% FV = $1,107,073 = $42,261(1 + r)30; r = ($1,107,073 / $42,261)1/30 – 1 = 0.1150, or 11.50% Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 5 $280 ±$372 N I/Y PV PMT FV Solve for 5.85% Enter 19 $400 ±$1,370 N I/Y PV PMT FV Solve for 6.69% Enter 20 $43,000 ±$238,809 N I/Y PV PMT FV Solve for 8.95% Enter 30 $42,261 ±$1,107,073 N I/Y PV PMT FV Solve for 11.50%
Previous: For each of the following, compute the future value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 2,500 12 12 % $ 9,252 6 10 81,355 13 11 188,796 7 7 Explanation: To find the FV of a lump sum, we use: FV = PV(1 + r)t FV = $2,500(1.12)12 = $ 9,739.94 FV = $9,252(1.10)6 = $ 16,390.48 FV = $81,355(1.11)13 = $ 315,924.26 FV = $188,796(1.07)7 = $ 303,165.12 Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 12 12% ±$2,500 N I/Y PV PMT FV Solve for $9,739.94 Enter 6 10% ±$9,252 N I/Y PV PMT FV Solve for $16,390.48 Enter 13 11% ±$81,355 N I/Y PV PMT FV Solve for $315,924.26 Enter 7 7% ±$188,796 N I/Y PV PMT FV Solve for $303,165.12
$
0
0
For each of the following, compute the present value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)):
 
Present ValueYears  Interest Rate Future value
$        12      6% $ 15,051 
       3      12    47,557 
       28      13    882,073 
       30      10    546,164 



Explanation:

Solve for the unknown interest rate in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 280 5 % $ 372 400 19 1,370 43,000 20 238,809 42,261 30 1,107,073 Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for r, we get: r = (FV / PV)1 / t – 1 FV = $372 = $280(1 + r)5; r = ($372 / $280)1/5 – 1 = 0.0585, or 5.85% FV = $1,370 = $400(1 + r)19; r = ($1,370 / $400)1/19 – 1 = 0.0669, or 6.69% FV = $238,809 = $43,000(1 + r)20; r = ($238,809 / $43,000)1/20 – 1 = 0.0895, or 8.95% FV = $1,107,073 = $42,261(1 + r)30; r = ($1,107,073 / $42,261)1/30 – 1 = 0.1150, or 11.50% Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 5 $280 ±$372 N I/Y PV PMT FV Solve for 5.85% Enter 19 $400 ±$1,370 N I/Y PV PMT FV Solve for 6.69% Enter 20 $43,000 ±$238,809 N I/Y PV PMT FV Solve for 8.95% Enter 30 $42,261 ±$1,107,073 N I/Y PV PMT FV Solve for 11.50%

Next: Solve for the unknown number of years in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 510 9 % $ 1,212 760 10 1,629 17,900 17 260,563 21,000 15 391,887 Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for t, we get: t = ln(FV / PV) / ln(1 + r) FV = $1,212 = $510(1.09)t; t = ln($1,212/ $510) / ln(1.09) = 10.04 years FV = $1,629 = $760(1.10)t; t = ln($1,629/ $760) / ln(1.10) = 8.00 years FV = $260,563 = $17,900(1.17)t; t = ln($260,563 / $17,900) / ln(1.17) = 17.06 years FV = $391,887 = $21,000(1.15)t; t = ln($391,887 / $21,000) / ln(1.15) = 20.94 years Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 9% $510 ±$1,212 N I/Y PV PMT FV Solve for 10.04 Enter 10% $760 ±$1,629 N I/Y PV PMT FV Solve for 8.00 Enter 17% $17,900 ±$260,563 N I/Y PV PMT FV Solve for 17.06 Enter 15% $21,000 ±$391,887 N I/Y PV PMT FV Solve for 20.94
Previous: For each of the following, compute the present value (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future value $ 12 6 % $ 15,051 3 12 47,557 28 13 882,073 30 10 546,164 Explanation: To find the PV of a lump sum, we use: PV = FV / (1 + r)t PV = $15,051 / (1.06)12 = $ 7,479.89 PV = $47,557 / (1.12)3 = $ 33,850.13 PV = $882,073 / (1.13)28 = $ 28,794.41 PV = $546,164 / (1.10)30 = $ 31,299.87 Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 12 6% $15,051 N I/Y PV PMT FV Solve for $7,479.89 Enter 3 12% $47,557 N I/Y PV PMT FV Solve for $33,850.13 Enter 28 13% $882,073 N I/Y PV PMT FV Solve for $28,794.41 Enter 30 10% $546,164 N I/Y PV PMT FV Solve for $31,299.87
$
0
0
Solve for the unknown interest rate in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)):
 
Present ValueYears Interest Rate Future Value
 $ 280  5       %     $ 372 
   400  19                1,370 
   43,000  20                238,809 
   42,261  30                1,107,073 



Explanation:
We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is:
 
FV = PV(1 + r)t
 
Solving for r, we get:
r = (FV / PV)1 / t– 1
  
FV = $372 = $280(1 + r)5; r = ($372 / $280)1/5– 1= 0.0585, or 5.85%
FV = $1,370 = $400(1 + r)19; r = ($1,370 / $400)1/19– 1= 0.0669, or 6.69%
FV = $238,809 = $43,000(1 + r)20; r = ($238,809 / $43,000)1/20– 1= 0.0895, or 8.95%
FV = $1,107,073 = $42,261(1 + r)30; r = ($1,107,073 / $42,261)1/30– 1= 0.1150, or 11.50%

Calculator Solution:

Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation.

Enter
5
$280
±$372

N
I/Y
PV
PMT
FV
Solve for
5.85%

Enter
19
$400
±$1,370

N
I/Y
PV
PMT
FV
Solve for
6.69%

Enter
20
$43,000
±$238,809

N
I/Y
PV
PMT
FV
Solve for
8.95%

Enter
30
$42,261
±$1,107,073

N
I/Y
PV
PMT
FV
Solve for
11.50%

Solve for the unknown number of years in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 510 9 % $ 1,212 760 10 1,629 17,900 17 260,563 21,000 15 391,887 Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for t, we get: t = ln(FV / PV) / ln(1 + r) FV = $1,212 = $510(1.09)t; t = ln($1,212/ $510) / ln(1.09) = 10.04 years FV = $1,629 = $760(1.10)t; t = ln($1,629/ $760) / ln(1.10) = 8.00 years FV = $260,563 = $17,900(1.17)t; t = ln($260,563 / $17,900) / ln(1.17) = 17.06 years FV = $391,887 = $21,000(1.15)t; t = ln($391,887 / $21,000) / ln(1.15) = 20.94 years Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 9% $510 ±$1,212 N I/Y PV PMT FV Solve for 10.04 Enter 10% $760 ±$1,629 N I/Y PV PMT FV Solve for 8.00 Enter 17% $17,900 ±$260,563 N I/Y PV PMT FV Solve for 17.06 Enter 15% $21,000 ±$391,887 N I/Y PV PMT FV Solve for 20.94

Next: Assume that in January 2010, the average house price in a particular area was $276,400. In January 2002, the average price was $193,300. What was the annual increase in selling price? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Annual increase in selling price % Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for r, we get: r = (FV / PV)1 / t – 1 r = ($276,400 / $193,300)1/8 – 1 = 0.0457, or 4.57% Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 8 $193,300 ±$276,400 N I/Y PV PMT FV Solve for 4.57%
Previous: Solve for the unknown interest rate in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 280 5 % $ 372 400 19 1,370 43,000 20 238,809 42,261 30 1,107,073 Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for r, we get: r = (FV / PV)1 / t – 1 FV = $372 = $280(1 + r)5; r = ($372 / $280)1/5 – 1 = 0.0585, or 5.85% FV = $1,370 = $400(1 + r)19; r = ($1,370 / $400)1/19 – 1 = 0.0669, or 6.69% FV = $238,809 = $43,000(1 + r)20; r = ($238,809 / $43,000)1/20 – 1 = 0.0895, or 8.95% FV = $1,107,073 = $42,261(1 + r)30; r = ($1,107,073 / $42,261)1/30 – 1 = 0.1150, or 11.50% Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 5 $280 ±$372 N I/Y PV PMT FV Solve for 5.85% Enter 19 $400 ±$1,370 N I/Y PV PMT FV Solve for 6.69% Enter 20 $43,000 ±$238,809 N I/Y PV PMT FV Solve for 8.95% Enter 30 $42,261 ±$1,107,073 N I/Y PV PMT FV Solve for 11.50%
$
0
0
Solve for the unknown number of years in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)):
 
 Present ValueYearsInterest RateFuture Value
 $ 510  9% $ 1,212 
   760  10    1,629 
   17,900  17    260,563 
   21,000  15    391,887 



Explanation:

Assume that in January 2010, the average house price in a particular area was $276,400. In January 2002, the average price was $193,300. What was the annual increase in selling price? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Annual increase in selling price % Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for r, we get: r = (FV / PV)1 / t – 1 r = ($276,400 / $193,300)1/8 – 1 = 0.0457, or 4.57% Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 8 $193,300 ±$276,400 N I/Y PV PMT FV Solve for 4.57%

Previous: Solve for the unknown number of years in each of the following (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)): Present Value Years Interest Rate Future Value $ 510 9 % $ 1,212 760 10 1,629 17,900 17 260,563 21,000 15 391,887 Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for t, we get: t = ln(FV / PV) / ln(1 + r) FV = $1,212 = $510(1.09)t; t = ln($1,212/ $510) / ln(1.09) = 10.04 years FV = $1,629 = $760(1.10)t; t = ln($1,629/ $760) / ln(1.10) = 8.00 years FV = $260,563 = $17,900(1.17)t; t = ln($260,563 / $17,900) / ln(1.17) = 17.06 years FV = $391,887 = $21,000(1.15)t; t = ln($391,887 / $21,000) / ln(1.15) = 20.94 years Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 9% $510 ±$1,212 N I/Y PV PMT FV Solve for 10.04 Enter 10% $760 ±$1,629 N I/Y PV PMT FV Solve for 8.00 Enter 17% $17,900 ±$260,563 N I/Y PV PMT FV Solve for 17.06 Enter 15% $21,000 ±$391,887 N I/Y PV PMT FV Solve for 20.94
$
0
0
Assume that in January 2010, the average house price in a particular area was $276,400. In January 2002, the average price was $193,300.
  
What was the annual increase in selling price? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
 
  Annual increase in selling price %  


Explanation:
We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is:
 
FV = PV(1 + r)t
 
Solving for r, we get:
r = (FV / PV)1 / t– 1
r = ($276,400 / $193,300)1/8– 1 = 0.0457, or 4.57%

Calculator Solution:

Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation.

Enter
8
$193,300
±$276,400

N
I/Y
PV
PMT
FV
Solve for
4.57%

Gore Range Carpet Cleaning is a family-owned business in Eagle-Vail, Colorado. For its services, the company has always charged a flat fee per hundred square feet of carpet cleaned.

Previous: Assume that in January 2010, the average house price in a particular area was $276,400. In January 2002, the average price was $193,300. What was the annual increase in selling price? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Annual increase in selling price % Explanation: We can use either the FV or the PV formula. Both will give the same answer since they are the inverse of each other. We will use the FV formula, that is: FV = PV(1 + r)t Solving for r, we get: r = (FV / PV)1 / t – 1 r = ($276,400 / $193,300)1/8 – 1 = 0.0457, or 4.57% Calculator Solution: Note: Intermediate answers are shown below as rounded, but the full answer was used to complete the calculation. Enter 8 $193,300 ±$276,400 N I/Y PV PMT FV Solve for 4.57%
$
0
0
Gore Range Carpet Cleaning is a family-owned business in Eagle-Vail, Colorado. For its services, the company has always charged a flat fee per hundred square feet of carpet cleaned. The current fee is $22.15 per hundred square feet. However, there is some question about whether the company is actually making any money on jobs for some customers—particularly those located on more remote ranches that require considerable travel time. The owner’s daughter, home for the summer from college, has suggested investigating this question using activity-based costing. After some discussion, a simple system consisting of four activity cost pools seemed to be adequate. The activity cost pools and their activity measures appear below:

  Activity Cost Pool               Activity Measure    Activity for the Year       
  Cleaning carpetsSquare feet cleaned (00s) 13,000 hundred square feet  
  Travel to jobsMiles driven 273,000 miles
  Job supportNumber of jobs  2,000 jobs
  Other (organization-sustaining
    and idle capacity costs)
None Not applicable


     The total cost of operating the company for the year is $363,000, which includes the following costs:

   
  Wages$ 148,000   
  Cleaning supplies  30,000   
  Cleaning equipment depreciation  14,000   
  Vehicle expenses  28,000   
  Office expenses  63,000   
  President’s compensation  80,000   
 

  Total cost$ 363,000   
 





     Resource consumption is distributed across the activities as follows:

 
Distribution of Resource Consumption Across Activities  
 Cleaning CarpetsTravel to JobsJob SupportOtherTotal
  Wages 78% 11%0% 11%100%
  Cleaning supplies100%0%0% 0%100%
  Cleaning equipment depreciation 74%0%0% 26%100%
  Vehicle expenses0% 81%0% 19%100%
  Office expenses0%0% 58% 42%100%
  President’s compensation0%0% 34% 66%100%


Job support consists of receiving calls from potential customers at the home office, scheduling jobs, billing, resolving issues, and so on.

Required:
1.
Prepare the first-stage allocation of costs to the activity cost pools. (Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)

          Cleaning
         Carpets
         Travel to Jobs     Job
       Support
          Other        Total
  Wages$  $  $  $  $  
  Cleaning supplies     
  Cleaning equipment depreciation     
  Vehicle expenses     
  Office expenses     
  President’s compensation     
 




  Total cost$   $  $  $  $  
 











2.Compute the activity rates for the activity cost pools. (Round your answers to 2 decimal places. Omit the "$" sign in your response.)

  Activity Cost PoolActivity Rate                                 
  Cleaning carpets$  per hundred square feet
  Travel to jobs$  per mile
  Job support$  per job


3.
The company recently completed a 8 hundred square-foot carpet-cleaning job at the Lazy Bee Ranch—a 52.00-mile round-trip from the company’s offices in Eagle-Vail. Compute the cost of this job using the activity-based costing system. (Round your intermediate and final answers to 2 decimal places. Omit the "$" sign in your response.)

  Cost       $  

4.
The revenue from the Lazy Bee Ranch was $177.20 (8 hundred square-feet at $22.15 per hundred square feet). Prepare a report showing the margin from this job. (Input all amounts as positive values except losses which should be indicated by a minus sign. Round your intermediate and final answers to 2 decimal places. Omit the "$" sign in your response.)

Gore Range Carpet Cleaning
Customer Margin—Activity-Based Costing
  Sales   $  
  Costs:  
      Cleaning carpets  $   
      Travel to jobs    
      Job support    
 

  Customer margin $  
  




Explanation:

Pro Golf Corporation produces private label golf clubs for pro shops throughout North America. The company uses activity-based costing to evaluate the profitability of serving its customers. This analysis is based on categorizing the company’s costs as follows, using the ease of adjustment color coding scheme.

$
0
0
Pro Golf Corporation produces private label golf clubs for pro shops throughout North America. The company uses activity-based costing to evaluate the profitability of serving its customers. This analysis is based on categorizing the company’s costs as follows, using the ease of adjustment color coding scheme.
   
 Ease of
Adjustment Code
  Direct materials             Green
  Direct labor             Yellow
  Indirect labor             Yellow
  Factory equipment depreciation             Red
  Factory administration             Red
  Selling and administrative wages and salaries             Red
  Selling and administrative depreciation             Red
  Marketing expenses             Yellow

   
      Management would like to evaluate the profitability of a particular customer—the Peregrine Golf Club of Eagle, Colorado. Over the last 12 months this customer submitted 2 order for 90 golf clubs that had to be produced in 2 batches due to differences in product labeling requested by the customer. Summary data concerning the order appear below:
   
  
  Number of clubs  90  
  Number of orders 2  
  Number of batches 2  
  Direct labor-hours per club .30  
  Selling price per club$52.00  
  Direct materials cost per club$24.60  
  Direct labor rate per hour$22.00  

   
     A cost analyst working in the controller's office at the company has already produced the action analysis cost matrix for the Peregrine Golf Club that follows:
   
  Action Analysis Cost Matrix for Peregrine Golf Club
 
Activity Cost Pools
 
 VolumeBatch ProcessingOrder ProcessingCustomer ServiceTotal  
  Activity 27.00 direct labor-hours 2
batches
2
order
1
customer
 
  Manufacturing overhead:          
       Indirect labor$34.00  $51.80  $5.00  $0.00  $90.80  
       Factory equipment depreciation 103.20   .70   0.00   0.00   103.90  
       Factory administration 15.40   .60   12.00   221.00   249.00  
  Selling and administrative overhead:          
       Wages and salaries 13.00   0.00   35.00   388.00   436.00  
       Depreciation 0.00   0.00   4.00   20.00   24.00  
       Marketing expenses 116.40   0.00   60.00   372.00   548.40  
 









  Total$282.00  $53.10  $116.00  $1,001.00  $1,452.10  
 




















   
Required:
Prepare an action analysis report showing the profitability of the Peregrine Golf Club. Include direct materials and direct labor costs in the report. (Round your answers to 2 decimal places. Input all amounts as positive values except losses which should be indicated by a minus sign. Omit the "$" sign in your response.)
   
Peregrine Golf Club
  Sales $  
  Green costs:  
       Direct materials$  
 

  Green margin  
  Yellow costs:  
       Direct labor  
       Indirect labor  
       Marketing expenses  
 

  Yellow margin  
  Red costs:  
       Factory equipment depreciation  
       Factory administration  
       Selling and administrative wages and salaries  
       Selling and administrative depreciation  
 

  Red margin $  
  




Explanation:

Pryad Corporation makes ultra-lightweight backpacking tents. Data concerning the company's two product lines appear below:

$
0
0
Pryad Corporation makes ultra-lightweight backpacking tents. Data concerning the company's two product lines appear below:
 
 Deluxe Standard
  Direct materials per unit$ 82 $ 51 
  Direct labor per unit$ 12.40 $ 9.50 
  Direct labor-hours per unit  .80 DLHs  1.00 DLHs
  Estimated annual production 25,000 units 30,000 units

  
      The company has a traditional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours for the upcoming year appear below:
 
   
  Estimated total manufacturing overhead $310,000 
  Estimated total direct labor-hours50,000 DLHs

 
Required:
1.
Determine the unit product costs of the Deluxe and Standard products under the company's traditional costing system. (Round your intermediate and final answers to 2 decimal places. Omit the "$" sign in your response.)

       Deluxe      Standard
  Unit product cost$  $  


2.
The company is considering replacing its traditional costing system for determining unit product costs for external reports with an activity-based costing system. The activity-based costing system would have the following three activity cost pools:
 
  
Expected Activity
  Activities and Activity Measures Estimated
Overhead Cost
DeluxeStandardTotal
  Supporting direct labor (direct labor-hours)$ 175,000    20,000    30,000    50,000  
  Batch setups (setups) 66,700    180    110   290  
  Safety testing (tests) 68,300    29    71   100  
 

   
  Total manufacturing overhead cost$310,000      
 



   

  
      Determine the unit product costs of the Deluxe and Standard products under the activity-based costing system. (Round your intermediate and final answers to 2 decimal places. Omit the "$" sign in your response.)

     Deluxe    Standard
  Unit product cost$  $  



Explanation:

Speedy Parcel Service operates a fleet of delivery trucks in a large metropolitan area. A careful study by the company’s cost analyst has determined that if a truck is driven 147,000 miles during a year, the average operating cost is 8.7 cents per mile. If a truck is driven only 98,000 miles during a year, the average operating cost increases to 9.6 cents per mile.

$
0
0
Speedy Parcel Service operates a fleet of delivery trucks in a large metropolitan area. A careful study by the company’s cost analyst has determined that if a truck is driven 147,000 miles during a year, the average operating cost is 8.7 cents per mile. If a truck is driven only 98,000 miles during a year, the average operating cost increases to 9.6 cents per mile.

Required:
1.
Using the high-low method, estimate the variable and fixed cost elements of the annual cost of truck operation. (Round the "Variable cost per mile" to 3 decimal places and the "Fixed cost" to the nearest dollar amount. Omit the "$" sign in your response.)

   
  Variable cost$  per mile
  Fixed cost$  per year


2.
Express the variable and fixed costs in the form Y = a + bX. (Round the "Variable cost per mile" to 3 decimal places and the "Fixed cost" to the nearest dollar amount. Omit the "$" sign in your response.)

  Y  =$  +$  X

3.
If a truck were driven 122,000  miles during a year, what total cost would you expect to be incurred? (Round the "Variable cost per mile" to 3 decimal places. Round your intermediate and final answers to the nearest dollar amount. Omit the "$" sign in your response.)

  Total annual cost$  


Explanation:

Alden Company has decided to use a contribution format income statement for internal planning purposes. The company has analyzed its expenses and has developed the following cost formulas:

$
0
0
Alden Company has decided to use a contribution format income statement for internal planning purposes. The company has analyzed its expenses and has developed the following cost formulas:

  CostCost Formula
  Cost of goods sold   $27 per unit sold
  Advertising expense   $184,000 per quarter
  Sales commissions   7% of sales
  Administrative salaries   $94,000 per quarter
  Shipping expense     ?
  Depreciation expense   $64,000 per quarter


     Management has concluded that shipping expense is a mixed cost, containing both variable and fixed cost elements. Units sold and the related shipping expense over the last eight quarters are given below:

  QuarterUnits SoldShipping
Expense
  Year 1:  
      First 30,000 $174,000      
      Second 32,000 $189,000      
      Third 37,000 $231,000      
      Fourth 33,000 $194,000      
  Year 2:  
      First 31,000 $184,000      
      Second 34,000 $199,000      
      Third 44,400 $246,000      
      Fourth 41,400 $222,000      


     Management would like a cost formula derived for shipping expense so that a budgeted contribution format income statement can be prepared for the next quarter.

Required:
1.
Using the high-low method, estimate a cost formula for shipping expense based on the data for the last eight quarters above. (Omit the "$" sign in your response.)

  Y = $ + $ X

2.
In the first quarter of Year 3, the company plans to sell 37,000 units at a selling price of $55 per unit. Prepare a contribution format income statement for the quarter. (Input all amounts as positive values except losses which should be indicated by a minus sign. Omit the "$" sign in your response.)

Alden Company
Budgeted Income Statement
For the First Quarter of Year 3
  Sales $  
  Variable expenses:  
       Cost of goods sold$   
       Shipping expense  
       Sales commissions  
 
 
  Total variable expenses  
  
  Contribution margin  
  Fixed expenses:  
       Shipping expense  
       Advertising expense  
       Administrative salaries  
       Depreciation expense  
 
 
  Total fixed expenses  
  
  Net operating income $  
  




Explanation:1.
High-low method:
 Units Sold Shipping Expense
  High activity level 44,400    $ 246,000    
  Low activity level 30,000      174,000    
 
 

  Change 14,400    $ 72,000    
 

 





Variable cost per unit=
Change in cost
Change in activity

=
$72,000
 = $5 per unit
14,400 units

Fixed cost element:
   
  Total shipping expense at high activity level$ 246,000   
  Less variable element:
    44,400 units × $5.00 per unit
  222,000   
 

  Fixed cost element$ 24,000   
 





Therefore, the cost formula is: Y = $24,000 + $5X.

2.
Sales: (37,000 units × $55 per unit) = $2,035,000
Cost of goods sold: (37,000 units × $27 per unit) = $999,000
Shipping expense: (37,000 units × $5 per unit) = $185,000
Sales commission: ($2,035,000 × .07) = $142,450
Viewing all 553 articles
Browse latest View live


<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>