The following tasks are to be performed on an assembly line:

$
0
0
The following tasks are to be performed on an assembly line:

TASK SECONDSTASKS THAT MUST PRECEDE
A 18          
B 12          A
C 10          B
D 14          B
E 26          C
F 28          D
G 15          E-F
H 15          G

 
The workday is 8.75 hours long. Demand for completed product is 900 per day.
 
Required:
(a)Find the cycle time. (Round your answer to 1 decimal place.)

  Cycle time seconds per unit  
 
(b)What is the theoretical number of workstations? (Round your answer to the next whole number.)

  Number of workstations 
 
(c)Balance the line using the longest-operating-time rule. (Leave no cells blank - be certain to enter "0" wherever required.Round your answers to 1 decimal place.)

Work stationTaskIdle time
IA-B
II D-C
III F
IV E
V G-H

 
(d)What is the efficiency of the line balanced as in (c)? (Round your answer to 1 decimal place. Omit the "%" sign in your response.)

  Efficiency %  
 
(e)Suppose that demand rose from 900 to 1,000 units per day. What would you do? (Round your answer to the nearest whole number.)

  Reduce cycle time to seconds, which may require rebalancing the line.
 
(f)Suppose that demand rose from 900 to 1,100 units per day. What would you do? (Round your answer to the nearest whole number.)

  Reduce cycle time to seconds, which may require rebalancing the line.


Explanation: