Sahtlam Ltd. (Sahtlam) is a small construction company in northern Ontario. Sahtlam recently signed a contract to build a new town hall in one of the region’s larger cities. Sahtlam will receive $26,600,000 from the city for building the town hall and will have to pay the costs of construction from that amount. |
Construction will begin in September 2017 and is expected to be completed in March 2019. Sahtlam’s year-end is December 31. Sahtlam estimates that construction costs in each year will be: |
2017 | 2018 | 2019 | Total | |
Estimated costs | $4,000,000 | $9,600,000 | $5,000,000 | $18,600,000 |
The city paid $8,000,000 when the contract was signed and will pay $6,200,000 on January 1, 2018, 2019, and 2020. |
Required:
Calculate the amount of revenue and expense that Sahtlam would recognize in each year of the contract using the percentage-of-completion and zero-profit methods. Assume the actual costs incurred equal the estimated costs. (Do not round intermediate calculations and round final answers to nearest whole dollar amount. Enter your percentage answers to 2 decimal places.)